Arbitration Grace Boeing

      
      - - - - - - - - - - - - - - - - - - - - - - -X
      : In the Matter of the Arbitration Between
      :    COMPANIES SUD-AMERICANA DE VAPORES       :
      :        as Disponent Owners of the
      :            "GRACE BOEING"                  :
      :             ---  and  ---
      :      COMPANIA MINERA CORDILLERA S.A.       :
      :            as Charterers
      :     Charter Party Dated July 31, 1980      :
      - - - - - - - - - - - - - - - - - - - - - - -X
      
      
      
      No. 2598
      September 19, 1989
      
      
      PANEL:  Mr. Hammond L. Cederholm;
              Captain Evangelos Rigos;
              Mr. Chas. F. Nisi,
              Chairman
      
      
      COUNSEL:  Representing Charterers: Bingham, Dana & Gould
                Michael J. Rauworth, Esq.
                Of Counsel
      
      Representing Owners: Kirlin, Campbell & Keating
                           J. Scot Provan, Esq.
                           Kevin L. Barren, Esq.
                           Thomas H. Walsh, Jr., Esq.
                           Of Counsel
      
      
      
      DECISION: FINAL AWARD
      
      
      FACTS:
      
          On July 31, 1980,  COMPANIA  SUD-AMERICANA  DE  VAPORES,  Valparaiso,  as
      Disponent Owner of the M/V GRACE BOEING ( hereinafter "Owner" ) chartered the
      vessel to COMPANIA MINERA CORDILLERA S.A. of Panama (hereinafter "Charterer")
      on a MEDITERRANEAN IRON ORE form of Charter Party,  for the transportation of
      35,000 long tons of road salt,  (10% more or less owner's option) for loading
      in Chile and discharge at Portsmouth, New Hampshire.
      
          The vessel loaded and performed it's  voyage  to discharge  port  without
      dispute,  however,  delays were encountered in discharging the cargo,   which
      resulted  in  Owner   presenting  it's  demurrage  claim  in  the  amount  of
      $ 32,456.25,  ( which was later adjusted by Owner to $ 31,675.35 ) which  was
      disputed by Charterer, thus the subject of this Arbitration.
      
      
      ARGUMENTS :
      
          The vessel arrived  Portsmouth  at 0304 hours of September 20, 1980.  The
      Master tendered Notice of Readiness, which was accepted at 1305 hours without
      reservation and laytime commenced 0800 hours on Monday,   September 22, 1980,
      unchallenged by Charterer.
      
         The vessel commenced discharge at 1500 hours on September 20th and was not
      completed until 1000 hours September 29th.
      
         As per Clause 5 of the Charter,the allowed time for discharge was six days
      and twenty hours (undisputed).
      
         Since the time allowed to discharge was exceeded by two days, twelve hours
      and  fortynine  minutes,  and the rate of demurrage was $ 12,500 per day,  in
      accordance with Clause 8 of the Charter,  Owner submitted it's claim  in  the
      amount of $ 31,675.35.
      
      
      CHARTERER'S CONTENTIONS:
      
          Charterer claims that  an ILA strike  condition  existed  throughout  the
      discharge operation,  specifically affecting the Crane operators,    who they
      claim,  were " key " to the discharge operation and since Charterer could not
      hire their  " regular "  experienced  crane operators,  they  had  to  employ
      " management level  and  irregular laborers ",  which  resulted  in  crippled
      efficiency. Consequently, Charterer relies on Clause 5 asserting that even if
      only 13 1/2 hours of discharge time could have been saved with  " efficient "
      labor,the vessel would have finished over the week-end and no demurrage would
      have been incurred.
      
      
      OWNER'S CONTENTIONS:
      
          Statements of Facts and Port Logs,   signed by the Master and also agents
      for both Owner and Charterer, make no mention of a Strike,  or time lost as a
      result of lack of labor.
      
          The discharge terminal was non-union,hence it would have been against the
      Law if ILA pickets prevented,  or interfered with,  employees  attempting  to
      cross the picket line, therefor the Terminal Operator ( Granite State ) could
      have gotten an immediate injunction vacating the Pickets, which was not done.
          Owner contends that  " informational picketting ",  where a Union informs
      me Public about a non-union shop,or illegal labor practices,is not a "strike"
      within the meaning of Clause 5 of the Charter,and Charterer was remiss in not
      taking more agressive methods to obtain suitable labor.
      
          Owner further observes that if there was a noticable  slow  down  in  the
      discharge operation caused by a " strike ", there would have been appropriate
      notations added to the Pod Log by Owners and Charterer's agents.
          Owner  also  provided  an  affidavit  by  the local Union President, that
      " informational pickets " were never more than 4 men and that there was never
      any interference with workers or vehicles ... and that there was "no strike".
      
      
      DELIBERATIONS :
      
          The record showed that on September 19th,the day before vessel's arrival,
      NLRB had certified ILA as exclusive bargaining representative for the workers
      at the discharge terminal whose operator (Granite State) failed to recognize,
      or bargain with ILA,  contending election irregularities,  therefor,  Granite
      State was subject to unfair labor practice actions at the time the vessel was
      in port,   despite the fact that Granite State was vindicated and all charges
      dropped 18 months later (Granite Stat's operation never has become Unionized).
      
          After  review of all evidence,   correspondance and affidavits, the Panel
      Majority (Mr. Cederholm dissenting) concludes as follows:
      
          1. There was a  " strike/labor  resistance "  condition  existing  at the
      terminal during vessel's discharge.
         2. ILA Picket activity deprived Granite State of part of it's regular work
      force. At least two of the pickets were "Regular" Crane Operators critical to
      efficient operations in this small two crane discharge work force.
          3. Charterer's  were  forced  to  hire  " management  level and irregular
      laborers", as a consequence resulting in crippled efficiency.
          4. The Panel Majority is satisfied that efficiency suffered,  at least to
      the extent of 13 1/2 hours,  therefor,  were it not for the  " strike/labor "
      condition,  vessel could have completed over the week-end in "excepted" time,
      in accordance with Clause 5, and no demurrage would have been incurred.
      
      
      AWARD:
      
          It is therefor the Majority Opinion, and is so ordered that:
          A. Owner's demurrage claim is rejected.
      
          B. Each Party is to absorb it's own Legal and all other expenses.
      
          The Panel assesses it's total fees at $ 3,600.00,  and while in the first
      instance, the fees shall be payable by each Party immediately mailing a check
      to each Arbitrator in the amount of $ 600.00,  full liability for  the  total
      fees is joint and several.  Should either Party fail to make full payment  of
      his portion within 15 days from receipt of this Award,  upon  demand  by  the
      Chairman the other Party will make the defaulting Party's  payment  and  will
      have a  claim-over against the non-payer,  plus 10 1/2% per  annum  pro  rata
      interest until full payment is recovered.
      
         This Award is fully binding on all Parties and can be reduced to judgement
      in any Court of competent jourisdiction.
      
      
          Dated at New York, N.Y.
      
      
      
      DISSENTBY:
      
      
      CEDERHOLM
      
      
      DISSENT: APPENDIX A
      
      
      M/V GRACE BOEING
      
      
      Dissent re Alleged Strike Affecting Discharge
      
      
      
          Clause 5 provides that  " time lost "  by reason of a strike  can  be  an
      exception to the running of laytime. However,   most of us experienced in the
      shipping industry know that such words  are  conditioned  by  some  important
      factors.The most obvious condition, to even a casual observer,is that someone
      claiming the benefit of this exception must prove that time actually was lost.
      The other requirement is that  before  a  Charterer  can  seek  credit for an
      exception,   he must prove he made efforts to overcome or avoid or ameliorate
      the effects of the exception,it is elementary that he cannot sit on his hands
      and do nothing and say he is automatically entitled to credit just because one
      of  numerous  laytime  exceptions  appears  to  have arisen.  That  mandatory
      requirement  by  Charterer  implies  certain consequences he must  bear  when
      meeting this obligation.
      
          The Majority is granting this award without any customary evidence  being
      produced by Charterer that any time  was  actually  lost  in  this  discharge
      operation. Furthermore, they are rewarding  Charterer  and  penalizing  Owner
      unfairly when Charterer merely complied with its  legal and contractual  duty
      of minimizing the results of an exception,  if  indeed ,  one  arose  in this
      situation. Holman's 16th Edition says:
      
          "In all cases,  it is up to the  Charterer  to  prove  that  an  excepted
      contingency occurred during the ... discharge operation.   He must also prove
      that its occurrence actually delayed the operation...
      
          The  unloading  of  this  vessel  by  Charterer's pier operator was not a
      labor-intensive operation,because the total labor force only consisted of six
      or seven personnel, four of whom operate two cranes in two shifts. Evidently,
      100 previous ships have all been handled the same way. Charterer's whole case
      is their undocumented allegation that during this supposed strike,two or more
      of their crane operators went on strike and the substitutes  they  hired  and
      their management personnel who carried on the  uninterrupted  operation  were
      slower in performance by at least 13 1/2 hours than 104 previous vessels where
      they had never exceeded laytime.
      
          No proof whatsoever was presented of who are their regular employees,  or
      who, if any, of same were actually on strike. The Court of Appeals overturned
      the union's attempt to  represent  these  few  people  when irregularities in
      balloting showed there was not a majority of the six or seven interested   in
      being unionized. To this date, the pier is non-union.
      
          No evidence whatsoever was presented to prove that 104 previous discharge
      were so efficient that they never  exceeded  allowed  laytime.   No  credible
      indication was given to the panel of what a  normal  discharge  could  be  or
      should be with this type of vessel, so that a comparison could be made to see
      if alleged strike conditions made this a slower operation  vis-a-vis all past
      ones.
      
         The sole "evidence" presented by Charterers are affidavits by their agent,
      their counsel and their pier operator and his assistant saying that there were
      so-called strike conditions that required substitute crane operators who were
      slower than their regulars, and this resulted in demurrage on the vessel.
      
          But none of this is "best evidence" which the law requires all  claimants
      must produce to prove the validity of their claim.  Each of these persons was
      in  the  employ  of  Charterer  so  what  they  say  is  hardly  objective or
      disinterested, and is not entitled to any weight in these proceedings.We have
      Charterer saying "these are my allegations and these employees  of  mine  all
      support me, so I am correct."For all we know,this might have been the fastest
      and  most  efficient  discharge  that  ever  took  place on this pier.  It is
      impossible  to  understand  how  the Majority can accept such unsubstantiated
      testimony.
      
          Charterer and Owner each had their respective port agents  for  discharge
      who jointly signed the Statement of Facts and Port Log along with the Master.
      No mention is made of any strike or any slowdowns account of  labor problems,
      although  Charterer's agent did try to  gain  some  laytime  credit  for  its
      principal by appending a few theoretical crane hours for loading stores after
      all three parties had signed the Port Log without such notations. Although it
      was highly improper to alter the report unilaterally in this manner, it shows
      that  Charterer's  agent  tried  to protect them from the loss of a few hours
      laytime,  so  they  certainly would have recorded any major loss of stevedore
      efficiency if indeed there had been any.
      
          Costly, sophisticated shore cranes cannot be operated by inexperienced or
      casual labor,because great damages could be inflicted on the vessel and shore
      installation by unskilled operators.When Owner pointed out the absence of any
      damages anywhere and even the relatively few hours in the total discharge lost
      by employing alleged irregulars during the so-called strike,Charterer quickly
      retorted that, of course,they had hired"qualified"crane drivers replacements.
      Well, it is obvious that these "qualified" crane drivers  ( denotes skill and
      experience)are as good as the other two "qualified" regular crane drivers who
      may have been absent during this operation,  which deflates the argument that
      time was lost when one substituted for the other.
      
          Since  Charterer  had  the  obligation to try to overcome or minimize the
      strike exception,  they  did  so when their pier operator carried on as usual
      with qualified replacement personnel.  The  duty  to  make  these  reasonable
      efforts to prevent the operation of the strike  exception  implies  that  the
      alternate or substitute place of unloading or mode of discharge may not be as
      perfect as the original one.But as long as it is reasonably close in time and
      cost as it was here,  Charterer  cannot  ask for credits that wipe out Owners
      demurrage legitimately earned  under  terms of the charter party.  Stevedores
      have exceptions for strikes or causes beyond their control in their contracts
      with Charterers whereby they can  invoice  Charterer  for  a  less  efficient
      operation than contemplated when they are forced to alternative procedures to
      accommodate Charterers.  No  such  extra  charges  were ever produced here or
      mentioned. If the pier operator did not suffer enough from a slow down to get
      extra compensation from Charterer, how can the Majority reason that Charterer
      was damaged by doing their  contractual  duty  that  shows from every aspect,
      there were no unreasonable results during this discharge.
      
          The  dictionary  defines,  and  Charterers  concur,  that  a  strike is a
      concerted refusal of labor  to  go  on working to compel an employer to grant
      certain demands. There was no concerted refusal here.The whole operation went
      on  as  usual  while  a  couple  union  pickets were conducting informational
      advertising to say they were interested in trying to organize this pier. They
      never convinced the pier workers because it remains non-union to this day.The
      head  of  the  local  union who supposedly carried on this alleged strike had
      these  remarks  to  say  in  his  affidavit  which  contradict  most  of what
      Charterer's pier operator swore to:
      
          " ILA Local 1947 held an information pickett near the entrance of Granite
      State Pier. The pickett usually consisted of one or two union members holding
      signs. -- There was no  interference with any workers or vehicles going in or
      out of the pier. -- At the time,the pier gave every appearance of business as
      usual.  Off  loading  operations  went  on every time there was a ship at the
      pier.-- There was no strike at the Granite State Pier at any time that I know
      of. -- The ILA never interfered with the business of Granite State. -- Again,
      the  picket  held was an information pickett only and created no problems for
      the Granite State"
      
          I had to elaborate on this whole scenario to show the overwhelming weight
      of the evidence that contravenes the unjust decision of the Majority in  this
      matter. There is no legal or evidentiary basis to support their award and the
      Owner is being wrongfully denied the demurrage he is due under the charter
      
      
      
      party.
      
      Hammond L. Cederholm
      
      
      
      
      

RETURN. to RIGOS home page