Arbitration Skyros CP 06/07/90



- - - - - - - - - - - - - - - - - - - - - - - - - - X
:        In the Matter of the Arbitration Between   :
:            ALLIED BULK NAVIGATION LTD.            :
:              Owner of the M/V SKYROS              :        FINAL AWARD
:                                                   :
:                    ---- and ----                  :                           :
:                                                   :
:         MMI INTERNATIONAL, INC., Charterer        :
: Under a GENCON Charter party, dated June 7 1970.  :
- - - - - - - - - - - - - - - - - - - - - - - - - - X




Before:   Jack Berg, Capt. E. Rigos and Donald Zubrod (Chair)

          Peter Skoufalos, Esq. (Chalos & Brown) for MMI         
          International, Inc.

          Eugene J. O'Connor, Esq. (Freehill, Hogan & Mahar) for      
          Allied Bulk Navigation Ltd.



INTRODUCTION

    This arbitration is  between  ALLIED BULK NAVIGATION LTD.,  ( hereinafter
" ABN " or " Owner " ),  as disponent owner of the bulk carrier M/V SKYROS, a
Maltese flag bulk vessel of 32,280 MT deadweight, and MMI INTERNATIONAL, INC.
( hereinafter " MMI " or " Charterer " ), as charterer under a GENCON form of
charter party, dated June 7, 1990.

    The charter party described the cargo to be lifted as 25,000 long tons of
bulk steel scrap,  5% more or less in Owner's option,  loading one safe berth
Tacoma, Washington for discharge at one safe berth, one safe port South Korea.
The vessel was ordered to discharge at Pusan.


THE PROCEEDING

    The panel was first asked  to address  the threshold question of  whether
the parties had entered into a fully effective and legally binding settlement
agreement capping the amount of damages which ABN would have   to pay MMI for
the alleged  cargo gear problem.   On August 9,  1993,    the panel majority,
Capt. Rigos dissenting,   issued a Partial Final Award in favor of Charterer,
concluding there had been no legally binding settlement agreement.  The panel
noted there were  significant negotiations between  the parties on this point
but that no agreement was ever concluded. See SMA 2998 (1993).

    This Final Award will now address  ABN's  substantative  defenses  to the
claims  and  the proper measure  of MMI's  damages,  if any.  The schedule of
presentations called for ABN  to submit its  substantive  defenses  within 30
days of the Partial Final Award  and for MMI  to offer  its rebuttal position
30 days thereafter. The submissions were made to the panel, as scheduled, the
last on September 30, 1993.


THE CLAIMS

     MMI's  claims for  additional  expenses  attributable to  the cargo gear
deficiency are as follows:
          Cargo gear load test    ----------   $  2,165.00
          Survey of gear     ---------------        500.00
          Stevedore standby cost   ---------     27,600.00
          Extra discharge costs  -----------    135,846.12
                    Despatch   -------------     13,750.00
                                               ------------
                                               $179,861.12

    MMI claims interest on the above,   the cost of  this arbitration and its
attorney's fees.

    ABN contends it owes only $4,336.70.


ARGUMENT

     ABN  questions  MMI's r ight  under  Clause 25  to order  the vessel  to
discharge at  anchorage K-20 when  the  receiver's  private berth,  the Hanbo
Pier,  was unavailable upon the vessel's arrival.  Furthermore,  ABN contends
the  anchorage was  unsafe for  the SKYROS,  therefore,  the Master had every
right to refuse to proceed there for discharge.

    MMI  maintains  Clause 38  permits it to  lighter  the vessel,   with the
expense for its own account, and further argues there is no basis to construe
Clause 38 as one which  limits lighterage  to alongside a berth as opposed to
at an anchorage.

    With respect to the gear capacity,  ABN contends  it previously  conceded
the inadequacy of the cargo cranes  solely for  its threshold application  to
the panel on the settlement agreement issue. ABN now contends the cargo  gear
was in accordance with  the requirements  of Clause 29,  and  points  to  the
vessel having passed its quadrennial cargo gear survey just six months  prior
to its arrival at Pusan. Furthermore,ABN argues that  an independent surveyor
criticized the methodology Charterer's  surveyor employed to  test  the  gear
after the Pusan stevedores complained of insufficient lifting capacity.

    MMI submits the evidence demonstrates the gear was incapable of complying
with the minimum eight metric ton weight requirement warranted in  clause 29.
Furthermore,  in no instance did Owner's surveyor ever attempt to  lift  that
weight.

    MMI contends  it suffered damages in the amount of $179,861.12,  and that
the additional costs are  the result of  ABN's  failure  to comply  with  the
Clause 29 cargo gear warranty.   MMI contends the above amount represents its
cost over and above what it would have incurred had it been able to discharge
the vessel as contemplated, utilizing ship's gear.

   ABN contends MMI's alleged damages are vastly overstated and has submitted
its own detailed calculation of the financial consequences of the   operation
had MMI correctly ordered the vessel to discharge at Pier 7 (Berth 73) rather
than improperly directing it to the X-20 anchorage. Assuming the ship's  gear
could not be used,  ABN  maintains  MMI would  have incurred additional costs
using shore cranes, trucks, etc.  but that the discharge at Pier 7 would have
completed much sooner. It is ABN's position that this procedure shortened the
discharge  by  about  23  days,    thereby   reducing   ABN's    sponsibility
significantly.


DISCUSSION AND DECISION

     The issues which are before the panel in this second and final phase  of
the arbitration are those raised by ABN  in defense of MMI's  claim.   Stated
briefly, they are:
          1. Was MMI permitted under the charter to order the 
             vessel to lighten at an anchorage;
          
          2. Was the designated lightering anchorage a safe one;
          
          3. Was the vessel's cargo gear capacity as warranted
             in the charter party; and
          
          4. Are MMI's damages overstated.
          
    Clauses 25 and 38 are pertinent to  the  question  of whether  MMI had  a
right to direct the vessel to the K-20 anchorage for partial discharge.   ABN
relies mainly on the language of Clause 25, arguing that MMI is  required  to
discharge at a berth, and that an anchorage is not a berth within the meaning
of the Clause. Clause 25 states:
          Vessel is to discharge at one (1) safe berth,  one (1)
          safe port South Korea. Discharging port to be declared
          on vessel's arrival at the load port.
          
    MMI contends it had the right to lighten the vessel  at its expense   and
that anchorage K-20 was a permissible location for the vessel to be lightened.
MMI relies mainly on Clause 38, which states:
          Lighterage, if any, either end, to be for Charterer's
          account.
          
    While MMI no doubt  preferred  utilizing  the receiver's  Hanbo Pier  for
discharge, it had the right to order discharge at any safe berth.  MMI   also
had the option of lighterage, if necessary, to enable the vessel to discharge
at the nominated berth.   Lightening operations are generally expected  to be
performed at safe anchorages and, in our unanimous view, they are permissible
unless the charter party expressly provides otherwise. It does not here.
  
    We may quickly dispose of the question of whether the anchorage was safe.
The fact is that there is ample evidence of similar vessels being assigned to
the K-20 anchorage on a regular basis and  there is  nothing of  substance to
suggest danger or unsafe conditions.   The Master stated  he  considered  the
anchorage was  unsafe  but there is nothing  specifically advanced to support
his  allegation.   In fact,   we believe  his  reluctance  to lighten  at the
anchorage had more to do with the vessel's cargo gear problem than the safety
of the anchorage itself. The panel unanimously agrees the nominated anchorage
was a safe one.
  
     We may also rapidly dispose of the cargo gear issue because the evidence
on this point is overwhelming. MMI has submitted surveys of established   and
experienced surveying firms attesting to  the inadequacy  of the  cargo gear.
Clause 29 provides in part:
        7 holds/hatches - 3 cranes of 8 tons serving hatches 2 through 7
        2 derricks at 8 tons serving number 1 hatch (all "about")
          
    ABN relies on statements contained in its surveyor's report   criticizing
MMI's surveyor's technique, but the argument is unpersuasive.  At no time did
ABN ever demonstrate the sufficiency of the cargo crane capacity by attempting
to lift the eight metric ton minimum capacity warranted in the charter party.
The panel unanimously concludes the cargo gear was not as warranted.
  
    With respect to MMI's damages, the panel majority, Capt. Rigos dissenting,
concludes that MMI's damages, as presented, are supported  by our findings of
fact and the documentation which MMI  has introduced.   Capt. Rigos'  partial
dissenting opinion is attached as Appendix A.
  
    ABN, in contesting MMI's damages,   relies upon a theoretical calculation
which takes into account the additional  expenses  of discharging  at Pier 7,
but which then credits back a saving of  approximately 23 days  at $5,500 per
day. The theory assumes MMI  would  have expended 44.14 days for the combined
discharge at K-20 anchorage and Hanbo Pier,   a procedure which MMI states it
would have followed if  the vessel's  cranes  were  in  accordance  with  the
warranted minimum lifting capacity. This is the exercise which appears in the
ABN's surveyor's report.
  
    The panel majority has reviewed the underlying computations and concludes
we are simply unable to accept the assumptions on which they are based.  They
are  speculative at best.   ABN's surveyor and an official of Owner's  London
representative  postulated  the  above theory in their  reports  but  neither
appeared before the panel to testify and be cross  examined  on  this  point.
Owner's London representative was scheduled to appear on two separate
occasions but cancelled both.   We,   therefore,  afford little weight to the
validity of the underlying premises and conclude  ABN's  theory of savings is
mere speculation.
  
    The panel majority awards MMI the sum of $179,861.12,   consisting of its
additional discharge expenses, despatch and other documented expenses.    The
balance of freight, less the overage insurance premium,   appear not to be in
dispute and this sum is credited to Owner.   We further award interest on the
net sum, at 7% per annum, from January 30, 1991, until the date of this award.
  
    MMI has argued right along that ABN's unreasonable position with  respect
to the alleged settlement agreement and the substance of other MMI claims have
unnecessarily prolonged the proceeding and made it far  more  costly  than it
should have been. MMI seeks an award of attorney's fees pursuant to Clause 47,
which expressly authorizes the arbitrators   "to award and/or apportion legal
costs to the successful party"  The panel majority concurs and awards MMI the
sum of $12,000 towards its attorney's fees.
  
  
  RECONCILIATION
  
    The following sums are awarded Charterer:
        1.   Additional expenses of discharge,
             despatch 6t documented expenses ....... $179,861.12
        2.   Less balance of freight with
             overage insurance credit ...............( 24,879.42)
        3.   Interest on net above at 7% p.a.
             from Jan. 31, 1991 to award date .......  32,248.75
        4.   Allowance of attorney's fees ............ 12,000.00
        5.   Credit for arbitrators' fees
             paid on behalf of Owner .................. 7,840.00
                                                     -------------
         Total due Charterer                         $207,070.45
  
    In the event the above sum is not paid within thirty days of the date  of
this award,   interest at 6% p.a.  shall  resume  on  the  principal   sum of
$154,981.70 from  the award date  until  it is paid  or reduced  to judgment,
whichever occurs first.
  
     The panel's fee is contained in attached Appendix B,   duly incorporated
herein, and payment is to be made pursuant to its terms.    Liability for the
arbitrators' fees is a joint and several obligation.
  
    The governing charter party specifies that the arbitrators' decision,  or
that of any two of them, shall be final, and for the purpose of enforcing any
award, the agreement may be made a rule of the court.
                              
  
  
  
  
  
                                              -----------------------------
                                                       Jack Berg
  
                                                                     
                                                                     
                                                                                                                                        
                                               ----------------------------
                                                   Captain E.N. Rigos
                                                  (Dissenting in part)
                               
                                                                     
                                                                      
                                               ----------------------------
                                                     Donald Zubrod,
                                                        Chairman
                                                                       
  
  
  
  New York, New York 
  January.21, 1994
  




















                              APPENDIX  C
                                    
  
  MV Skyros/MMI 
  CP 06/07/90 
  
                                                   DISSENTING OPINION
                                                           OF
                                                     CAPT.E.N.RIGOS
                                                                       
  
Based on the evidence presented to the panel,   and with all respect to  the
opinion of the other members, I disagree with their conclusion.  I am of the
pinion that there was a binding agreement between the two parties,   ABN and
MMI, involved in the arbitration.
  
On August 20,1990 the Owners of the vessel, ABN,   proposed without prejudice
the following:
        1.- All cargo to be discharged at Berth 73 using shore
        cranes ( and vessels's derricks if this required.)
  
        2.- Owners to contribute with 50 percent but maximum
        usd 30,000 towards any additional stevedoring/transportation
        etc costs incurred over and above what the cost would be if
        vessel discharged whole cargo at K-20 with her own gear and
        the remaining portion to be met by charterers/receivers.
  
        3.- Laytime from when berth 73 becomes available to count in
        accordance with the provisions of the C/P.
  
        4.- Time for the time between vessel's arrival at Pusan and
        the time berth 73 becomes available to count in half for
        laytime purposes.
  
        5.- First of the two shiftings made so far to be for owner's
        account. Shifting from waiting anchorage to berth 73 for owners'
        account. Any other shiftings in accordance with C/P provisions.

        6.- Any stevedore cancellation expenses incurred so far for
        charterers/receivers' account.
  
The same day August 20, 1990 the charterers reverted as follows:
" .... However,   in order to solve the present matter at Busan with a spirit
of goodwill and cooperation to minimize the possible damage to the  concerned
parties, we have agree with owner's proposal without prejudice."
  
On August 24, 1990  the owners send a fax to   Charterers advising them  that
receivers claimed USD 162,476 as extra cost.  In addition,  and with the same
document, the owners requested charterers "... whether the agreement made with
Charterers is to be followed by Charterers or not."
  
Charterers reverted  " ... Meantime,   please  refer  to  our previous fax of
August 20th, 1990 which will be followed by us."

On October 5, 1990 the Charterers of the vessel repudiated  the agreement  by
advising Owners as follows:
  
" We are regretfully forced to repudiate our agreement of   August 20th, 1990
which was made on a "without prejudice" basis, because the total claim amount
we are facing now is much greater than it was originally represented by you."
  
Although charterers, with their letter dated October 5, 1990,  repudiated the
agreement because it was made "without prejudice"  and because the amount was
greater than it was originally represented, I have noticed that owners advised
charterers for the increased amount on August 24, 1990 and charterers accepted
same.   Charterers were aware of the fact that the,   amount of the claim was
$162,476.

With reference to  "without prejudice"  statement in  their correspondence by
both parties, I am of the opinion that Charterers and Owners placed this term
in there communication in order to protect themselves  in any  unknown  claim
over and above the amount of $162,476.
  
As a conclusion,   I am of the view that there is a binding agreement and the
proposal  of  Owners  dated  August  20, 1990  was  accepted  by  Charterers,
Therefore,   this agreement is binding for both parties up to the  amount  of
$162,476.
  
  
  New York, N.Y.
  August 9 1993 



                                        Capt. E.N.Rigos
                                         (Dissenting)
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  

RETURN. to RIGOS home page